BCU-ITT-63595 - WREXHAM MAELOR HOSPITAL PHARMACY BOILER REPLACEMENT

Replace three existing Remeha Gas 210 ECO boilers with three new Remeha Gas 210 Ace 120/4 sectional boilers in the Pharmacy Plantroom at Wrexham Maelor Hospital. Works include pipework modification, BMS integration, electrical alterations, testing, commissioning, and all associated builders' works, delivered as a phased installation to maintain service continuity.

You'll want to look if you install and commission commercial gas boilers and have CDM Principal Contractor experience in hospital or healthcare settings

  • CDM Principal Contractor competence
  • Experience with gas boiler installation and commissioning
  • Building Management System integration capability

Honeywell UK Limited maintains the Building Management System across primary care sites at this buyer, as of August 2026. Inferred from prior awards to this buyer, not confirmed.