Contracts

Replacement of Steam Boilers

MHRA is replacing three gas-fired steam boilers with two electric steam boilers at their Potters Bar research facility. The work includes design, supply, installation, testing, commissioning and full mechanical, electrical, controls and civil enabling works.

  • NEC3 ECC Main Option A pricing required
  • must demonstrate safe delivery at live operational medical-research facility
  • social value commitments required
  • the contract itself is a large one

Honeyman Water Limited serviced clean steam generators for MHRA in November 2025, but no incumbent for boiler replacement work is evident from prior awards. Inferred from prior awards to this buyer, not confirmed.