Plowright Formaldehyde (HCOH) Detection System Replacement

Design and build a new formaldehyde detection system for The Plowright Building at Pirbright Institute, including detailed design, supply, installation, commissioning and a 15-year operational lifespan.

You'll want to look if you design and install gas detection systems or have experience with formaldehyde detection equipment and can manage the full design-to-build process including commissioning.

  • Must provide design drawings showing exact location and configuration
  • Must provide calibration method with tender
  • Must manage all subcontractors
  • Must deliver O&M manual covering design, risk assessment, hazardous materials, removal procedures and H&S information

Safety Gas Detection Limited won the Jenner Building CO2 Detection System Replacement for this buyer in December 2025. Inferred from prior awards to this buyer, not confirmed.