Hedgewood School - Classroom Rebuild works
Demolish an 80m² conservatory at Hedgewood School in Hayes and replace it with a new purpose-built extension. Work includes internal refurbishment of two classrooms, remodelling to create additional teaching spaces, and external works.
- Closed31 March 2026
- Value£350k
- BuyerLondon Borough of Hillingdon
- WhereHedgewood School, Weymouth Road, Hayes
- CategoryConstruction & building works
- RegionLondon
You'll want to look if you're a general contractor with school building or refurbishment experience and can work to JCT intermediate contracts with design liability
You'll need
- JCT 2024 Intermediate Building Contract with Contractors Design experience
- Suitably qualified and experienced works contractor
Possible incumbent
Loughton Contracts PLC won Meadow High School Expansion work for this buyer in September 2025. Inferred from prior awards to this buyer, not confirmed.