Copy of 5452 - Trinant Primary School - Boiler Replacement
Supply and install two new boilers and associated plant in the boiler room at Trinant Primary School, including removal of redundant services, insulation, and commissioning. Work must be completed within 4 weeks during term time with no loss of heating service.
- Closed7 October 2025
- Value£61k
- BuyerCaerphilly County Borough Council
- WhereTrinant Primary School
- CategoryConstruction & building works, Building materials & structures, Furniture, equipment & supplies, Surveying, architecture & engineering
- RegionWales
You'll want to look if you install heating systems and can coordinate boiler manufacturer commissioning, and can complete work in schools without disrupting service
You'll need
- Boiler manufacturer's commissioning engineers must be employed
- Detailed programme of works required at tender stage